Blocking in two steps
31.07.2023: Subarea marked “blue” in the plan
01.08.2023: Subarea marked “yellow” in the plan
02.08.2023: Junctions marked “green” in the plan
Asphalt paving at the end of the construction work from 31.07. until 2.08.2023
Beginning Monday, July 31, 2023 (start of service), through Wednesday, Aug. 2, 2023 (end of service), construction will be completed in Burgbergsiedlung with the installation of the asphalt overlay. On the three days it is not possible to drive to and around the Burgbergsiedlung with the buses and RufBussen. The stop “Jagstheim Burgbergsiedlung” will be completely relocated to the stop “Jagstheim Ortsmitte”.
The buses of the company Müller can not serve the stops “Alexandersreut” and “Degenbachsee” on the 3 days due to detour. These stops will be eliminated without replacement.
From Thursday, August 3, 2023, the construction work in the Burgbergsiedlung will be completed, and buses and RufBuses will then be able to operate regularly again.
Source: https://kreisverkehr-sha.de/aktuelles/verkehr/#jfmulticontent_c979-6